Six to ten weeks to a trading licence if nothing stalls. Here is the phase-by-phase reality, and what usually goes wrong.

Agents quote "two weeks for a PT PMA". That figure describes the notarial deed, not a company that can legally trade.

To a trading NIB with a genuine domicile secured, before any construction starts, budget 6 to 10 weeks.

The phases

PhaseNormalWhen it stalls
Structuring and classification mapping1–2 weeks
Incorporation: deed → decree → NPWP → domicile3–5 weeks8+ weeks
NIB and risk classification1–2 weeks
Bank account and capital injection2–3 weeks, runs in parallel
KKPR spatial validation2–4 weeks8–12 weeks
Operational licensing for the classification4–8 weeks3–4 months
PBG → construction → SLF10–16 weeks6+ months
Investor or work KITAS3–5 weeks8+ weeks

Read the right-hand column carefully. These are not rare edge cases — they are the ordinary outcome when one input is wrong at the start.

The capital position

Two separate numbers, routinely confused:

The gap between them is commonly bridged with a shareholder loan, subject to a 4:1 debt-to-equity cap. Paid-up capital also carries a 12-month retention requirement — it is not money you inject to satisfy a checkbox and withdraw the following month.

If your capital self-declaration does not reconcile with the actual bank transfer and the figures in the articles of association, the file stops. This is the single most common reason an incorporation runs to eight weeks instead of four.

The Bali gate

Before any of the above, one question decides whether the company can exist at all: is your intended activity open to a new foreign-owned company in Bali?

Since 22 July 2026, eighteen classifications are closed to new PMA registration — villa, café, real estate brokerage, hotels under 6,000 m², hotel management, vehicle rental among them. Apartment hotel and hotels above 6,000 m² remain open. The detail is here.

Discovering this at week six is expensive. Establish it at week zero.

What actually stalls files

The order that saves money

1. Confirm the classification is open, in Bali, today

2. Confirm the site's spatial position before committing to it

3. Then incorporate

4. Then permit

5. Then build

Most expensive failures come from doing step 3 first because it feels like progress.

Kai, Bali property adviser